FOUNDATIONS

Strip Footing calculator

Continuous footing volume and longitudinal bars.

YOUR MEASUREMENTS

Strip Footing

⌑
↻ Results update as you type
YOUR ESTIMATELIVE
Concrete volume
3.6m³
Cubic yards4.709 yd³
Straight longitudinal bars24 m
CONNECT TO COST, LABOUR & BOQ
Open BoQ ↗

An estimate for planning. Currency selection changes the display symbol only (no exchange-rate conversion). Verify measurements and product specifications before ordering.

THE FORMULAVolume = L × W × D; bar length = L × number of longitudinal bars
ASSUMPTIONSBar count is an input from your drawing, not a recommendation. Bar length excludes laps, hooks, bends, links and anchorage. This tool does not size foundations.
UNDERSTAND YOUR ESTIMATE

How to use the strip footing calculator

This calculator helps you measure continuous footing concrete and straight longitudinal reinforcement. It is intended for quantity takeoffs, early budgets and checks against a measured schedule. Start with the dimensions or quantities for one clearly defined item of work. Enter values in the units shown beside each field; millimetres and metres are not interchangeable.

Bar count is an input from your drawing, not a recommendation. Bar length excludes laps, hooks, bends, links and anchorage. This tool does not size foundations.

Step-by-step takeoff workflow

  1. Enter your measured dimensions and inputs: Input the project values for Length (m), Width (m), Depth / thickness (m), Longitudinal bars. Check that every measurement uses the exact unit shown beside its field.
  2. Review the live quantity and formula calculation: The calculator applies Volume = L × W × D; bar length = L × number of longitudinal bars immediately in your browser and displays the primary and secondary takeoff figures.
  3. Carry forward to cost, BoQ, CSV or printable takeoff sheet: Send your calculated quantity directly to Concrete Cost, Markup / Margin or the Bill of Quantities (BoQ) worksheet, or export via CSV and Print / PDF.

Worked example

A 10 m × 0.6 m × 0.3 m strip contains 1.8 m³. Four continuous straight bars need 40 m before detailing allowances.

Quick-reference lookup table

Quick reference: Strip footing concrete volume and straight 4-bar length per 10 m trench run
Footing width × depthCross-section areaConcrete per 10 m (m³)Volume (yd³)4 longitudinal bars (net)
450 mm × 225 mm0.101 m²1.01 m³1.32 yd³40.0 m
600 mm × 250 mm0.150 m²1.50 m³1.96 yd³40.0 m
600 mm × 300 mm0.180 m²1.80 m³2.35 yd³40.0 m
750 mm × 300 mm0.225 m²2.25 m³2.94 yd³40.0 m
900 mm × 350 mm0.315 m²3.15 m³4.12 yd³40.0 m

Before you order

Compare the result with your drawings and supplier information. Keep the original net quantity separate from allowances, and round purchasing quantities only at the ordering stage. Check whether delivery, labour and related materials belong elsewhere in your estimate. If the drawing or specification changes, update the inputs and record the revised basis instead of reusing an earlier total.

For the concepts behind this calculation, read Rebar (Reinforcement Steel), Lap Length, Takeoff (Quantity Takeoff).

Common questions & estimating checks

What formula does the strip footing calculator use?

Volume = L × W × D; bar length = L × number of longitudinal bars — Bar count is an input from your drawing, not a recommendation. Bar length excludes laps, hooks, bends, links and anchorage. This tool does not size foundations.

How do you work out a strip footing example?

A 10 m × 0.6 m × 0.3 m strip contains 1.8 m³. Four continuous straight bars need 40 m before detailing allowances.

Which inputs and units are required for this calculation?

You enter Length (m), Width (m), Depth / thickness (m), Longitudinal bars. Keep metres and millimetres distinct, and use the header currency selector to display monetary amounts in EUR, GBP, USD or a custom currency code.

What should I check before ordering materials from a strip footing estimate?

Verify dimensions against approved construction drawings, confirm supplier pack sizes and product yields, and keep net measured quantities separate from cutting or site wastage allowances.