How to use the strip footing calculator
This calculator helps you measure continuous footing concrete and straight longitudinal reinforcement. It is intended for quantity takeoffs, early budgets and checks against a measured schedule. Start with the dimensions or quantities for one clearly defined item of work. Enter values in the units shown beside each field; millimetres and metres are not interchangeable.
Bar count is an input from your drawing, not a recommendation. Bar length excludes laps, hooks, bends, links and anchorage. This tool does not size foundations.
Worked example
A 10 m × 0.6 m × 0.3 m strip contains 1.8 m³. Four continuous straight bars need 40 m before detailing allowances.
Before you order
Compare the result with your drawings and supplier information. Keep the original net quantity separate from allowances, and round purchasing quantities only at the ordering stage. Check whether delivery, labour and related materials belong elsewhere in your estimate. If the drawing or specification changes, update the inputs and record the revised basis instead of reusing an earlier total.
For the concepts behind this calculation, read Rebar (Reinforcement Steel), Lap Length, Takeoff (Quantity Takeoff).