Pad / Spread Footing calculator

Quantities for one pad or a repeated foundation.

YOUR MEASUREMENTS

Pad / Spread Footing

⌑
↻ Results update as you type
YOUR ESTIMATELIVE
Concrete volume
3.6m³
Cubic yards4.709 yd³
CONNECT TO COST, LABOUR & BOQ
Open BoQ ↗

An estimate for planning. Currency selection changes the display symbol only (no exchange-rate conversion). Verify measurements and product specifications before ordering.

THE FORMULAVolume = length × width × depth × quantity
ASSUMPTIONSMeasures rectangular pads of uniform depth. Blinding, pedestals, excavation and sloping faces are separate items. Use dimensions from an approved design.
UNDERSTAND YOUR ESTIMATE

How to use the pad / spread footing calculator

This calculator helps you calculate concrete quantities for one or more rectangular pad foundations. It is intended for quantity takeoffs, early budgets and checks against a measured schedule. Start with the dimensions or quantities for one clearly defined item of work. Enter values in the units shown beside each field; millimetres and metres are not interchangeable.

Measures rectangular pads of uniform depth. Blinding, pedestals, excavation and sloping faces are separate items. Use dimensions from an approved design.

Step-by-step takeoff workflow

  1. Enter your measured dimensions and inputs: Input the project values for Length (m), Width (m), Depth / thickness (m), Quantity. Check that every measurement uses the exact unit shown beside its field.
  2. Review the live quantity and formula calculation: The calculator applies Volume = length × width × depth × quantity immediately in your browser and displays the primary and secondary takeoff figures.
  3. Carry forward to cost, BoQ, CSV or printable takeoff sheet: Send your calculated quantity directly to Concrete Cost, Markup / Margin or the Bill of Quantities (BoQ) worksheet, or export via CSV and Print / PDF.

Worked example

Four pads measuring 1.5 m × 1.5 m × 0.5 m contain 4.5 m³ in total.

Quick-reference lookup table

Quick reference: Isolated pad foundation concrete volume by base dimensions
Pad L × W × Depth1 pad volume (m³)4 pads volume (m³)8 pads volume (m³)Plan bearing area
1.0 m × 1.0 m × 0.40 m0.40 m³1.60 m³3.20 m³1.00 m²
1.2 m × 1.2 m × 0.45 m0.65 m³2.59 m³5.18 m³1.44 m²
1.5 m × 1.5 m × 0.50 m1.13 m³4.50 m³9.00 m³2.25 m²
1.8 m × 1.8 m × 0.60 m1.94 m³7.78 m³15.55 m³3.24 m²
2.0 m × 2.0 m × 0.65 m2.60 m³10.40 m³20.80 m³4.00 m²

Before you order

Compare the result with your drawings and supplier information. Keep the original net quantity separate from allowances, and round purchasing quantities only at the ordering stage. Check whether delivery, labour and related materials belong elsewhere in your estimate. If the drawing or specification changes, update the inputs and record the revised basis instead of reusing an earlier total.

For the concepts behind this calculation, read Takeoff (Quantity Takeoff), Measured Works, Concrete Grade.

Common questions & estimating checks

What formula does the pad / spread footing calculator use?

Volume = length × width × depth × quantity — Measures rectangular pads of uniform depth. Blinding, pedestals, excavation and sloping faces are separate items. Use dimensions from an approved design.

How do you work out a pad / spread footing example?

Four pads measuring 1.5 m × 1.5 m × 0.5 m contain 4.5 m³ in total.

Which inputs and units are required for this calculation?

You enter Length (m), Width (m), Depth / thickness (m), Quantity. Keep metres and millimetres distinct, and use the header currency selector to display monetary amounts in EUR, GBP, USD or a custom currency code.

What should I check before ordering materials from a pad / spread footing estimate?

Verify dimensions against approved construction drawings, confirm supplier pack sizes and product yields, and keep net measured quantities separate from cutting or site wastage allowances.