MASONRY & FINISHES

Screed calculator

From coverage and thickness to mix and bags.

YOUR MEASUREMENTS

Screed

▦
↻ Results update as you type
YOUR ESTIMATELIVE
Mix volume
1.5m³
Whole bags to buy125 bags
CONNECT TO COST, LABOUR & BOQ
Open BoQ ↗

An estimate for planning. Currency selection changes the display symbol only (no exchange-rate conversion). Verify measurements and product specifications before ordering.

THE FORMULAVolume = area × thickness / 1000; bags = ceil(volume / yield)
ASSUMPTIONSUses a uniform finished thickness and a user-entered mixed yield per bag. The default yield is illustrative; proprietary mixes vary. Substrate levelling, multiple coats and wastage require separate allowances.
UNDERSTAND YOUR ESTIMATE

How to use the screed calculator

This calculator helps you calculate screed volume and bag quantities from floor area and thickness. It is intended for quantity takeoffs, early budgets and checks against a measured schedule. Start with the dimensions or quantities for one clearly defined item of work. Enter values in the units shown beside each field; millimetres and metres are not interchangeable.

Uses a uniform finished thickness and a user-entered mixed yield per bag. The default yield is illustrative; proprietary mixes vary. Substrate levelling, multiple coats and wastage require separate allowances.

Step-by-step takeoff workflow

  1. Enter your measured dimensions and inputs: Input the project values for Net area (m²), Coat thickness (mm), Yield per bag (m³). Check that every measurement uses the exact unit shown beside its field.
  2. Review the live quantity and formula calculation: The calculator applies Volume = area × thickness / 1000; bags = ceil(volume / yield) immediately in your browser and displays the primary and secondary takeoff figures.
  3. Carry forward to cost, BoQ, CSV or printable takeoff sheet: Send your calculated quantity directly to Concrete Cost, Markup / Margin or the Bill of Quantities (BoQ) worksheet, or export via CSV and Print / PDF.

Worked example

At 30 m², each 10 mm of thickness requires 0.3 m³. A 50 mm screed therefore needs 1.5 m³ before wastage.

Quick-reference lookup table

Quick reference: Floor screed mix volume and bags (at 0.012 m³/bag) for a 30 m² floor
Screed thicknessNet mix volume (m³)With 5% waste (m³)Bags (0.012 m³ net)Typical screed type
35 mm1.05 m³1.10 m³88 bagsBonded cement-sand screed
50 mm1.50 m³1.58 m³125 bagsUnbonded screed on membrane
65 mm1.95 m³2.05 m³163 bagsFloating screed over insulation (domestic)
75 mm2.25 m³2.36 m³188 bagsFloating screed or underfloor heating
100 mm3.00 m³3.15 m³250 bagsHeavy-duty levelling screed

Before you order

Compare the result with your drawings and supplier information. Keep the original net quantity separate from allowances, and round purchasing quantities only at the ordering stage. Check whether delivery, labour and related materials belong elsewhere in your estimate. If the drawing or specification changes, update the inputs and record the revised basis instead of reusing an earlier total.

For the concepts behind this calculation, read Screed, Wastage Factor, Unit Rate.

Common questions & estimating checks

What formula does the screed calculator use?

Volume = area × thickness / 1000; bags = ceil(volume / yield) — Uses a uniform finished thickness and a user-entered mixed yield per bag. The default yield is illustrative; proprietary mixes vary. Substrate levelling, multiple coats and wastage require separate allowances.

How do you work out a screed example?

At 30 m², each 10 mm of thickness requires 0.3 m³. A 50 mm screed therefore needs 1.5 m³ before wastage.

Which inputs and units are required for this calculation?

You enter Net area (m²), Coat thickness (mm), Yield per bag (m³). Keep metres and millimetres distinct, and use the header currency selector to display monetary amounts in EUR, GBP, USD or a custom currency code.

What should I check before ordering materials from a screed estimate?

Verify dimensions against approved construction drawings, confirm supplier pack sizes and product yields, and keep net measured quantities separate from cutting or site wastage allowances.